Aproject currently in progress has a cost today of $28,205 the estimated cost to complete he project is $11,210, the contract price for the project is $51,500. using the percentage of completion method of accounting, what is the revenue earned?

answer
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 22:50, rydersasser12
Awork system has five stations that have process times of 5, 9, 4, 9, and 8. what is the throughput time of the system? a. 7b. 4c. 18d. 35e. 9
Answers: 2
image
Business, 23.06.2019 08:20, megandalolipop
As task uncertainty and interdependence increase, are a more effective coordination mechanism than
Answers: 3
image
Business, 23.06.2019 09:50, JeroMii
Provide three examples of how the purpose of investing is different than the purpose of saving
Answers: 2
image
Business, 23.06.2019 22:30, misslux
In 2014, the average debt for college student loans is $28,700. this amounts to a $330 monthly payment for a "standard" loan repayment plan over 10 years. what monthly interest rate is being charged on this typical student loan?
Answers: 3
Do you know the correct answer?
Aproject currently in progress has a cost today of $28,205 the estimated cost to complete he project...

Questions in other subjects:

Konu
Mathematics, 14.09.2020 09:01
Konu
Mathematics, 14.09.2020 09:01
Konu
Mathematics, 14.09.2020 09:01
Konu
Mathematics, 14.09.2020 09:01
Konu
Mathematics, 14.09.2020 09:01
Konu
Health, 14.09.2020 09:01
Konu
Physics, 14.09.2020 09:01
Konu
Mathematics, 14.09.2020 09:01
Konu
Mathematics, 14.09.2020 09:01
Konu
Geography, 14.09.2020 14:01