Business, 24.12.2019 02:31, Mw3spartan17

The bank is working to develop an efficient work schedule for full-time and part-time tellers. the schedule must provide for efficient operation of the bank, including adequate customer service, employee breaks, and so on. on fridays, the bank is open from 9: 00 a. m. to 7: 00 p. m. the number of tellers necessary to provide adequate customer service during each hour of operation is summarized here. time no. of tellers time no. of tellers 9: 00 a. m.-10: 00 a. m. 6 2: 00 p. m.-3: 00 p. m. 6 10: 00 a. m.-11: 00 a. m. 4 3: 00 p. m.-4: 00 p. m. 4 11: 00 a. m.-noon 8 4: 00 p. m.-5: 00 p. m. 7 noon-1: 00 p. m. 10 5: 00 p. m.-6: 00 p. m. 6 1: 00 p. m.-2: 00 p. m. 9 6: 00 p. m.-7: 00 p. m. 6 each full-time employee starts on the hour and works a 4-hour shift, followed by a 1-hour break and then a 3-hour shift. part-time employees work one 4-hour shift beginning on the hour. considering salary and fringe benefits, full-time employees cost the bank $15 per hour ($105 a day), and part-time employees cost the bank $8 per hour ($32 per day).

time no. of tellers time no. of tellers
9: 00 a. m.-10: 00 a. m. 6 2: 00 p. m.-3: 00 p. m. 6
10: 00 a. m.-11: 00 a. m. 4 3: 00 p. m.-4: 00 p. m. 4
11: 00 a. m.-noon 8 4: 00 p. m.-5: 00 p. m. 7
noon-1: 00 p. m. 10 5: 00 p. m.-6: 00 p. m. 6
1: 00 p. m.-2: 00 p. m. 9 6: 00 p. m.-7: 00 p. m. 6
(a) formulate an integer programming model that can be used to develop a schedule that will satisfy customer service needs at a minimum employee cost. (hint: let xi = number of full-time employees coming on duty at the beginning of hour i and yi = number of part-time employees coming on duty at the beginning of hour i.)

(b) solve the lp relaxation of your model in part (a). if required, round your answers to the nearest whole number.

(c) solve for the optimal schedule of tellers.

(d) after reviewing the solution to part (c), the bank manager realized that some additional requirements must be specified. specifically, she wants to ensure that one full-time employee is on duty at all times and that there is a staff of at least five full-time employees. revise your model to incorporate these additional requirements, and solve for the optimal solution. if required, round your answers to the nearest whole number. the new optimal solution is as follows: i have tried the answers i have found from other posts and some are correct and others are not. could someone me solve this.

answer
Answers: 2

Other questions on the subject: Business

image
Business, 22.06.2019 10:30, gonzalesalexiaouv1bg
The advertisement demonstrates a popular way companies try to sell a product. what should consumers consider when it comes to the price of this product? it includes shipping and handling costs. it takes into account maintenance costs. it explains why this price is a good deal. it makes the full cost appears lower than it is.
Answers: 1
image
Business, 22.06.2019 12:10, montgomerykarloxc24x
The cost of the beginning work in process inventory was comprised of $3,000 of direct materials, $10,000 of direct labor, and $10,000 of factory overhead. costs incurred during the period were comprised of $15,000 of direct materials costs, and $100,000 of conversion costs. the equivalent units of production (eup) for the period were 9,000 for direct materials and 6,000 for conversion. the costs per eup were:
Answers: 3
image
Business, 22.06.2019 22:00, ethanw8973
Which of the following is a function performed by market prices? a. market prices communicate information to buyers and sellers. b. market prices coordinate the decisions of buyers and sellers. c. market prices motivate entrepreneurs to produce those products that are currently most desired relative to their costs of production. d. all of the above are functions performed by market prices.
Answers: 2
image
Business, 23.06.2019 00:30, darlene93
An emerging methodology to integrate the effort of the development team and the operations team to improve the functionality and security of applications is known as
Answers: 1
Do you know the correct answer?
The bank is working to develop an efficient work schedule for full-time and part-time tellers. the s...

Questions in other subjects:

Konu
Biology, 19.11.2020 01:00
Konu
Mathematics, 19.11.2020 01:00