You are working as a project manager in your organization. you are nearing the final stages of project execution and looking towards the final risk monitoring and controlling activities. for your project archives, which one of the following is an output of risk monitoring and control?
a. quantitative risk analysis
b. risk audits
c. requested changes
d. qualitative risk analysis

answer
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 13:30, 462nolan
Suppose the money market is in the liquidity trap and the fed increases the supply of money. individuals would rather hold than because they expect that bond prices can go no
Answers: 2
image
Business, 21.06.2019 20:30, ROBIOX3551
Which of the following is an example of formal management controls? answers: a firm's culturethe willingness of employees to monitor each otherbudgeting and reporting activitiesmanagerial motivation
Answers: 3
image
Business, 22.06.2019 11:20, jaideeplalli302
You decided to charge $100 for your new computer game, but people are not buying it. what could you do to encourage people to buy your game?
Answers: 1
image
Business, 22.06.2019 12:50, lily539711
Required information problem 15-1a production costs computed and recorded; reports prepared lo c2, p1, p2, p3, p4 [the following information applies to the questions displayed below. marcelino co.'s march 31 inventory of raw materials is $84,000. raw materials purchases in april are $540,000, and factory payroll cost in april is $364,000. overhead costs incurred in april are: indirect materials, $59,000; indirect labor, $26,000; factory rent, $38,000; factory utilities, $19,000; and factory equipment depreciation, $58,000. the predetermined overhead rate is 50% of direct labor cost. job 306 is sold for $670,000 cash in april. costs of the three jobs worked on in april follow. job 306 job 307 job 308 balances on march 31 direct materials $30,000 $36,000 direct labor 25,000 14,000 applied overhead 12,500 7,000 costs during april direct materials 133,000 210,000 $100,000 direct labor 105,000 150,000 101,000 applied overhead ? ? ? status on april 30 finished (sold) finished in process (unsold) required: 1. determine the total of each production cost incurred for april (direct labor, direct materials, and applied overhead), and the total cost assigned to each job (including the balances from march 31). a-materials purchases (on credit). b-direct materials used in production. c-direct labor paid and assigned to work in process inventory. d-indirect labor paid and assigned to factory overhead. e-overhead costs applied to work in process inventory. f-actual overhead costs incurred, including indirect materials. (factory rent and utilities are paid in cash.) g-transfer of jobs 306 and 307 to finished goods inventory. h-cost of goods sold for job 306. i-revenue from the sale of job 306. j-assignment of any underapplied or overapplied overhead to the cost of goods sold account. (the amount is not material.) 2. prepare journal entries for the month of april to record the above transactions. 3. prepare a schedule of cost of goods manufactured. 4.1 compute gross profit for april. 4.2 show how to present the inventories on the april 30 balance sheet.
Answers: 3
Do you know the correct answer?
You are working as a project manager in your organization. you are nearing the final stages of proje...

Questions in other subjects:

Konu
English, 28.07.2020 20:01