The project plan is supported by:
1. the work breakdown structure, the budget, and the work packages.
2. the work breakdown structure, the budget, and the schedule.
3. the work breakdown structure, the work packages, and the schedule.
4. the work breakdown structure, the schedule, and the contingency plan.

answer
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 02:30, leomessifanboy678
Witch is an example of a non durable good?
Answers: 1
image
Business, 22.06.2019 09:30, bubbagumpshrimpboy
When you hire an independent contractor you don't have to pay the contractors what
Answers: 3
image
Business, 22.06.2019 15:40, Zachary429
Brandt enterprises is considering a new project that has a cost of $1,000,000, and the cfo set up the following simple decision tree to show its three most likely scenarios. the firm could arrange with its work force and suppliers to cease operations at the end of year 1 should it choose to do so, but to obtain this abandonment option, it would have to make a payment to those parties. how much is the option to abandon worth to the firm?
Answers: 1
image
Business, 23.06.2019 00:40, maddie1776
Assume the total cost of a college education will be $250,000 when your child enters college in 17 years. you presently have $69,000 to invest. what annual rate of interest must you earn on your investment to cover the cost of your child’s college education? (do not round intermediate calculations. enter your answer as a percent rounded to 2 decimal places, e. g., 32.16.)
Answers: 2
Do you know the correct answer?
The project plan is supported by:
1. the work breakdown structure, the budget, and the work...

Questions in other subjects:

Konu
Mathematics, 12.10.2021 09:00
Konu
Biology, 12.10.2021 09:00