Business
Business, 18.12.2019 20:31, Dweath50

Which career pathway requires that employees have stamina, stress-management skills, confidence, persuasiveness, and specialized knowledge about a product or service? a. professional sales and marketing b. marketing information management and research c. marketing communications and promotion d. buying and merchandising

answer
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 18:30, mashejaj
2. high-glow currently produces 1,000 bicycles per month. the following per unit data apply for sales to regular customers: direct materials $50 direct manufacturing labor 5 variable manufacturing overhead 14 fixed manufacturing overhead 10 total manufacturing costs $79 the plant is experiencing demand shortage and is considering reducing production to 800 bicycles. what is the per unit cost of producing 800 bicycles? a) $79 per unit b) $81.50 per unit c) $74 per unit d) $69 per unit
Answers: 2
image
Business, 22.06.2019 10:00, lm942747
What is the difference between an "i" statement and a "you" statement? a. the "i" statement is non-confrontational b. the "you" statement is non-confrontational c. the "i" statement is argumentative d. the "you" statement is neutral in tone select the best answer from the choices provided
Answers: 1
image
Business, 22.06.2019 12:50, lily539711
Required information problem 15-1a production costs computed and recorded; reports prepared lo c2, p1, p2, p3, p4 [the following information applies to the questions displayed below. marcelino co.'s march 31 inventory of raw materials is $84,000. raw materials purchases in april are $540,000, and factory payroll cost in april is $364,000. overhead costs incurred in april are: indirect materials, $59,000; indirect labor, $26,000; factory rent, $38,000; factory utilities, $19,000; and factory equipment depreciation, $58,000. the predetermined overhead rate is 50% of direct labor cost. job 306 is sold for $670,000 cash in april. costs of the three jobs worked on in april follow. job 306 job 307 job 308 balances on march 31 direct materials $30,000 $36,000 direct labor 25,000 14,000 applied overhead 12,500 7,000 costs during april direct materials 133,000 210,000 $100,000 direct labor 105,000 150,000 101,000 applied overhead ? ? ? status on april 30 finished (sold) finished in process (unsold) required: 1. determine the total of each production cost incurred for april (direct labor, direct materials, and applied overhead), and the total cost assigned to each job (including the balances from march 31). a-materials purchases (on credit). b-direct materials used in production. c-direct labor paid and assigned to work in process inventory. d-indirect labor paid and assigned to factory overhead. e-overhead costs applied to work in process inventory. f-actual overhead costs incurred, including indirect materials. (factory rent and utilities are paid in cash.) g-transfer of jobs 306 and 307 to finished goods inventory. h-cost of goods sold for job 306. i-revenue from the sale of job 306. j-assignment of any underapplied or overapplied overhead to the cost of goods sold account. (the amount is not material.) 2. prepare journal entries for the month of april to record the above transactions. 3. prepare a schedule of cost of goods manufactured. 4.1 compute gross profit for april. 4.2 show how to present the inventories on the april 30 balance sheet.
Answers: 3
image
Business, 22.06.2019 18:00, mcckenziee
When peter metcalf describes black diamond’s manufacturing facility in china as a “greenfield project,” he means that partnered with a chinese company to buy the plant . of all market entry strategies, this one carries the lowest risk. because black diamond manufactures its outdoor sports products outside the united states, what risks must its managers be aware of?
Answers: 1
Do you know the correct answer?
Which career pathway requires that employees have stamina, stress-management skills, confidence, per...

Questions in other subjects:

Konu
Mathematics, 26.06.2020 22:01