Slack time in a network is the

a. time consuming job or task that is a key subpart of the total project.
b. shortest amount of time that could be required to complete the activity.
c. amount of time that you would expect it would take to complete the activity.
d. amount of time that an activity can be delayed without delaying the entire project.
e. none of the above

answer
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 14:00, darlinsanchez08com
In the context of your career choice, your own business skills cannot influence the level of your personal financial success. a. true b. false
Answers: 2
image
Business, 21.06.2019 21:00, CadenSkinner2003
The table shows the demand and supply schedules for magazines. complete the following sentences. the equilibrium price of a magazine is $ 4 and the equilibrium quantity is 150 magazines a week. price (dollars per magazine) quantity demanded quantity supplied (magazines per week) 3.00 160 138 3.50 155 144 4.00 150 150 4.50 145 156 5.00 140 161 now a fall in the price of a newspaper decreases the quantity demanded by 11 magazines a week at each price. at the original equilibrium price, a occurs. to return to equilibrium, the price of a magazine a. surplus; rises b. shortage; rises c. shortage; falls d. surplus; falls as the market returns to equilibrium, the quantity demanded and the quantity supplied a. decreases; increases b. decreases; decreases c. increases; decreases d. increases; increases the new equilibrium price is $ nothing a magazine.
Answers: 1
image
Business, 22.06.2019 02:40, shadow29916
Aquatic marine stores company manufactures special metallic materials and decorative fittings for luxury yachts that require highly skilled labor. aquatic uses standard costs to prepare its flexible budget. for the first quarter of the year, direct materials and direct labor standards for one of their popular products were as follows: direct materials: 3 pounds per unit; $ 6 per pound direct labor: 4 hours per unit; $ 19 per hour during the first quarter, aquatic produced 5 comma 000 units of this product. actual direct materials and direct labor costs were $ 65 comma 000 and $ 330 comma 000, respectively. for the purpose of preparing the flexible budget, calculate the total standard direct materials cost at a production volume of 5 comma 000 units.
Answers: 2
image
Business, 22.06.2019 05:40, rafa3997
According to the philosopher immanuel kant, the right of employees to know the nature of the job they are being hired to do and the obligation of a company not to deceive them in this respect is mainly reflective of the basic right of . privac yb. free consentc. freedom of speechd. freedom of consciencee. first refusal
Answers: 1
Do you know the correct answer?
Slack time in a network is the

a. time consuming job or task that is a key subpart of t...

Questions in other subjects: