Business, 14.12.2019 03:31, mimi8734

Cost of quality report

a quality control activity analysis indicated the following four activity costs of a hotel:

inspecting cleanliness of rooms $46,800
processing lost customer reservations 93,600
rework incorrectly prepared room service meal 70,200
employee training 23,400
total $234,000

sales are $1,800,000. prepare a cost of quality report. round percent of sales to one decimal place.

cost of quality report
quality cost quality cost percent of cost percent of
classification quality cost total sales
$ % %
prevention
appraisal
internal failure
external failure
total

answer
Answers: 1

Other questions on the subject: Business

image
Business, 21.06.2019 22:20, mistytownsend1952
Outstanding stock consists of 8,300 shares of cumulative 7% preferred stock with a $10 par value and 4,300 shares of common stock with a $1 par value. during the first three years of operation, the corporation declared and paid the following total cash dividends. year dividend declared 2016 $ 0 2017 $ 7,300 2018 $ 45,000 the amount of dividends paid to preferred and common shareholders in 2018 is:
Answers: 2
image
Business, 21.06.2019 23:30, khohenfeld0
Actual usage for the year by the marketing department was 70,000 copies and by the operations department was 330,000 copies. if a dual-rate cost-allocation method is used, what amount of copying facility costs will be budgeted for the operations department?
Answers: 2
image
Business, 22.06.2019 00:40, tenleywood
The silverside company is considering investing in two alternative projects: project 1 project 2 investment $500,000 $240,000 useful life (years) 8 7 estimated annual net cash inflows for useful life $120,000 $40,000 residual value $32,000 $10,000 depreciation method straightminusline straightminusline required rate of return 11% 8% what is the accounting rate of return for project 2? (round any intermediary calculations to the nearest dollar, and round your final answer to the nearest hundredth of a percent, x. xx%.)
Answers: 3
image
Business, 22.06.2019 14:20, kevinglvz
Anew 2-lane road is needed in a part of town that is growing. at some point the road will need 4 lanes to handle the anticipated traffic. if the city's optimistic estimate of growth is used, the expansion will be needed in 4 years and has a probability of happening of 40%. for the most likely and pessimistic estimates, the expansion will be needed in 8 and 15 years respectively. the probability of the pessimistic estimate happening is 20%. the expansion will cost $ 4.2 million and the interest rate is 8%. what is the expected pw the expansion will cost?
Answers: 1
Do you know the correct answer?
Cost of quality report

a quality control activity analysis indicated the following four...

Questions in other subjects:

Konu
Chemistry, 30.05.2021 01:00