Project umuc is to produce 200 widgets and is scheduled to take five weeks. each unit is planned to cost $90. the project is severely cost constrained. performance data for the project at the end of week three is presented below: • 120 total units were planned to be produced • 130 units have actually been produced • the financial manager reported that the business had actually spent $13,000 on the project by the end of week three. answer the following questions; show all work: a. quantify cost variance. is the project ahead or behind budget? b. quantify schedule variance. is the project ahead or behind schedule? c. quantify cost performance efficiency. is the project performing better or worse than planned? d. quantify schedule performance efficiency. is the project performing better or worse than planned? e. what is the forecast of project cost at completion assuming current cost performance efficiency remains the same? how much budget variance is expected at completion? f. what is the forecast of funding needed to complete the project (from this point forward)? g. what cost performance efficiency would be required for the remainder of the project to complete the project within the original budget? h. as the project financial manager, what recommendations would you make?

answer
Answers: 3

Other questions on the subject: Business

image
Business, 21.06.2019 14:20, fideldiazidea
The manager of a branch office of banco mexicali observed that during peak hours an average of 20 customers arrives per hour and that there is an average of 6 customers in the branch office at any time. how long does the average customer spend waiting in line and being serviced?
Answers: 2
image
Business, 21.06.2019 21:00, hannahkharel2
On june 1 of the current year, chad wilson established a business to manage rental property. he completed the following transactions during june: opened a business bank account with a deposit of $28,000 from personal funds. purchased office supplies on account, $2,690. received cash from fees earned for managing rental property, $7,390. paid rent on office and equipment for the month, $3,310. paid creditors on account, $1,230. billed customers for fees earned for managing rental property, $6,130. paid automobile expenses (including rental charges) for the month, $740, and miscellaneous expenses, $370. paid office salaries, $2,330. determined that the cost of supplies on hand was $1,590; therefore, the cost of supplies used was $1,100. withdrew cash for personal use, $2,210. required: 1. indicate the effect of each transaction and the balances after each transaction: for those boxes in which no entry is required, leave the box blank. for those boxes in which you must enter subtractive or negative numbers use a minus sign. (example: -300) answer
Answers: 1
image
Business, 22.06.2019 08:30, Maelynne8515
In risk management, what does risk control include? a. risk identification b. risk analysis c. risk prioritization d. risk management planning e. risk elimination need this answer now : (
Answers: 3
image
Business, 22.06.2019 18:00, kekoanabor19
Abbington company has a manufacturing facility in brooklyn that manufactures robotic equipment for the auto industry. for year 1, abbingtonabbington collected the following information from its main production line: actual quantity purchased-200 units, actual quantity used-110 units, units standard quantity-100 units, actual price paid-$8 per unit, standard price-$10 per unit. atlantic isolates price variances at the time of purchase. what is the materials price variance for year 1? 1. $400 favorable. 2. $400 unfavorable. 3. $220 favorable. 4. $220 unfavorable.
Answers: 2
Do you know the correct answer?
Project umuc is to produce 200 widgets and is scheduled to take five weeks. each unit is planned to...

Questions in other subjects:

Konu
Mathematics, 13.04.2021 17:40
Konu
Mathematics, 13.04.2021 17:40