Project managers must often face the challenge of compressing the project schedule. all of the following actions can be taken to reduce the duration of the critical path except:
a. overlap sequential activities using finish-to-finish, start-to-start, or start-to-finish relationships.
b. reduce the project scope and /or quality.
c. use the float in critical path activities
d. partially overlap sequential activities by using time leads.

answer
Answers: 2

Other questions on the subject: Business

image
Business, 22.06.2019 09:00, flore7488
Your grandmother told you a dollar doesn't go as far as it used to. she says the purchasing power of a dollar is much lesser than it used to be. explain what she means. try and use and explain terms like inflation and deflation in your answer.
Answers: 1
image
Business, 22.06.2019 15:00, cheyfaye4173
Oerstman, inc. uses a standard costing system and develops its overhead rates from the current annual budget. the budget is based on an expected annual output of 120,000 units requiring 480,000 direct labor hours.(practical capacity is 500,000 hours)annual budgeted overhead costs total $772,800, of which $556,800 is fixed overhead. a total of 119,300 units, using 478,000 direct labor hours, were produced during the year. actual variable overhead costs for the year were $260,400 and actual fixed overhead costs were $555,450.required: 1. compute the fixed overhead spending variance and indicate if favorable or unfavorable.2. compute the fixed overhead volume variance and indicate if favorable or unfavorable.
Answers: 3
image
Business, 22.06.2019 21:10, kalawson2019
You own a nonunion company with 93 nonexempt employees. all of these employ- ees pack books into boxes for shipment to customers throughout the united states. because of wide differences in performance, you have decided to try performance appraisal, something never done before. until now, you have given every worker the same size increase. now you want to measure performance and reward the best performers with bigger increases. without any further information, which of the five types of appraisal formats do you think would be most appropriate? justify your answer. do you anticipate any complaints, or other comments, from employees after you implement your new system?
Answers: 1
image
Business, 22.06.2019 23:10, jayjayw64
Tony prince is the project manager for the recreation and wellness intranet project. team members include you, a programmer/analyst and aspiring project manager; patrick, a network specialist; nancy, a business analyst; and bonnie, another programmer/analyst. other people are supporting the project from other departments, including yusaff from human resources and cassandra from finance. assume that these are the only people who can be assigned and charged to work on project activities. recall that your schedule and cost goals are to complete the project in six months for under $200,000.task 2identify at least eight milestones for the recreation and wellness intranet project. write a short paper describing each milestone using the smart criteria. discuss how determining these milestones might add activities or tasks to the gantt chart. remember that milestones normally have no duration, so you must have tasks that will lead to completing the milestone.
Answers: 3
Do you know the correct answer?
Project managers must often face the challenge of compressing the project schedule. all of the follo...

Questions in other subjects:

Konu
Mathematics, 24.02.2021 01:50
Konu
Mathematics, 24.02.2021 01:50
Konu
Chemistry, 24.02.2021 01:50
Konu
Social Studies, 24.02.2021 01:50