Abc construction has developed the following set of activities for its budgeting process.

activity

predecessor

normal activity time (days)

resulting activity time if activity is crashed (days)

total cost to complete activity in normal time

total cost to complete activity in crash time

a

--

4

2

$200

$600

b

a

6

3

$300

$1200

c

a

4

1

$300

$900

d

b, c

3

2

$500

$550

e

d

4

1

$500

$1700

a) using the normal times, what is the critical path and project completion time for the budgeting process? also, what is the cost to complete the project based on the normal times?

b) if we want to reduce the project completion time to the minimum possible time by crashing activities, what is the new project completion time and what is the new total project cost?

c) modify the problem as follows. there is now an indirect cost of $75 per day, which is in addition to the cost identified above. there is also a penalty cost of $200 per day for any project completion time over 11 days. what is the minimum cost schedule for the project and what is the total cost for this schedule? identify what are the time and the path of this minimum cost schedule.

d) suppose that the company wants to crash the project 4 days. based on the information provided in the table and in part c) and the results from part c), what would the minimum penalty cost have to be for this to be supported by the economics in the problem? assume that the indirect cost remains at $75 per day.

answer
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 11:30, khynia11
Given the following information about the closed economy of brittania, what is the level of investment spending and private savings, and what is the budget balance? assume there are no government transfers. gdp=$1180.00 million =$510.00 million =$380.00 million =$280.00 million
Answers: 3
image
Business, 22.06.2019 14:30, kaylahill14211
You hear your supervisor tell another supervisor that a fire drill will take place later today when the fire alarm sounds that afternoon you should
Answers: 1
image
Business, 22.06.2019 19:50, annabanana1298
Juan's investment portfolio was valued at $125,640 at the beginning of the year. during the year, juan received $603 in interest income and $298 in dividend income. juan also sold shares of stock and realized $1,459 in capital gains. juan's portfolio is valued at $142,608 at the end of the year. all income and realized gains were reinvested. no funds were contributed or withdrawn during the year. what is the amount of income juan must declare this year for income tax purposes?
Answers: 1
image
Business, 22.06.2019 20:00, lusa0720
Edna gomez is the founder of the restaurant chain good and green. she ensures that the products in her stores are ethically and responsibly sourced. most products are therefore 100 percent organic and all packaging is manufactured from recycled material. also, her company sources ingredients from farms within 100 miles from her locations. edna's belief is that her restaurants should be able to support the community at large. which of the following terms best describes edna gomez? a. headhunter b. category captain c. social entrepreneur d. trade creditor
Answers: 3
Do you know the correct answer?
Abc construction has developed the following set of activities for its budgeting process.