Which estimating technique decomposes the work into lower, more detailed pieces, preferably the lowest level of wbs work elements, for which estimates are prepared and then aggregates them into a total quantity for the project?

a. grass roots estimating
b. piece meal pricing
c. bottom-up estimating
d. decomposition estimating

answer
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 16:00, knownperson233
In macroeconomics, to study the aggregate means to study blank
Answers: 1
image
Business, 23.06.2019 02:20, mpgleboski
When the benefit of one particular use of a resource is greater than the opportunity cost, then that resource is which of the following? a. not scarce b. being used efficiently c. a normal good d. non-excludable
Answers: 2
image
Business, 23.06.2019 08:40, LaBreeska
One principle of usability testing is that it permeates product development. what does that mean?
Answers: 3
image
Business, 23.06.2019 16:30, joseestrada27
Consider the following potential events that might have occurred to global on december​ 30, 2016. for each​ one, indicate which line items in​ global's balance sheet would be affected and by how much. also indicate the change to​ global's book value of equity. a. global used $ 19.8$19.8 million of its available cash to repay $ 19.8$19.8 million of its​ long-term debt. b. a warehouse fire destroyed $ 4.9$4.9 million worth of uninsured inventory. c. global used $ 4.6$4.6 million in cash and $ 5.1$5.1 million in new​ long-term debt to purchase a $ 9.7$9.7 million building. d. a large customer owing $ 3.2$3.2 million for products it already received declared​ bankruptcy, leaving no possibility that global would ever receive payment. e. ​global's engineers discover a new manufacturing process that will cut the cost of its flagship product by more than 48 %48%. f. a key competitor announces a radical new pricing policy that will drastically undercut​ global's prices.
Answers: 2
Do you know the correct answer?
Which estimating technique decomposes the work into lower, more detailed pieces, preferably the lowe...

Questions in other subjects: