Your project to obtain charitable donations is now 36 days into a planned 46-day project. the project is divided into 3 activities. the first activity is designed to solicit individual donations. it is scheduled to run the first 31 days of the project and to bring in $25,100. even though we are 36 days into the project, we still see that we have only 90% of this activity complete. the second activity relates to company donations and is scheduled to run for 36 days starting on day 5 and extending through day 41. we estimate that even though we should have (31/36) 86% of this activity complete, it is actually only 58% complete. this part of the project was scheduled to bring in $150,100 in donations. the final activity is for matching funds. this activity is scheduled to run the last 10 days of the project and has not started. it is scheduled to bring in an additional $50,200. so far $175,600 has actually been brought in on the project. calculate the schedule variance, schedule performance index, cost variance and cost (actually value in this case) performance index. (negative values should be indicated by a minus sign. do not round intermediate calculations. round your dollar amounts to the nearest whole number. round your "performance index" values to 3 decimal places.) schedule variance $ schedule performance index cost variance $ cost performance index

answer
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 15:40, Zachary429
Brandt enterprises is considering a new project that has a cost of $1,000,000, and the cfo set up the following simple decision tree to show its three most likely scenarios. the firm could arrange with its work force and suppliers to cease operations at the end of year 1 should it choose to do so, but to obtain this abandonment option, it would have to make a payment to those parties. how much is the option to abandon worth to the firm?
Answers: 1
image
Business, 22.06.2019 18:00, judali
David paid $975,000 for two beachfront lots in coastal south carolina, with the intention of building residential homes on each. two years later, the south carolina legislature passed the beachfront management act, barring any further development of the coast, including david's lots. when david files a complaint to seek compensation for his property, south carolina refuses, pointing to a passage in david's own complaint that states "the beachfront management act [was] properly and validly designed to south carolina's " is south carolina required to compensate david under the takings clause?
Answers: 1
image
Business, 22.06.2019 20:20, tytybruce2
Carmen’s beauty salon has estimated monthly financing requirements for the next six months as follows: january $ 9,000 april $ 9,000 february 3,000 may 10,000 march 4,000 june 5,000 short-term financing will be utilized for the next six months. projected annual interest rates are: january 9 % april 16 % february 10 may 12 march 13 june 12 what long-term interest rate would represent a break-even point between using short-term financing and long-term financing?
Answers: 3
image
Business, 22.06.2019 22:50, sydneip6174
Suppose that the u. s. dollars-mexican pesos exchange rate is fixed by the u. s. and mexican governments. assume also that labor is mobile between the united states and mexico due to low transportation costs. which of the following situations is likely to happen as a result of a simultaneous increase in the demand for u. s. goods and decrease in the demand for mexican goods? (pick mexican unemployment rate increases, and the country undergoes bad economic times for a sustained u. s. unemployment rate increases, and the country undergoes bad economic times for a sustained mexican unemployment rate rises at first, but it soon drops as unemployed mexicans move to the united states for mexican unemployment rate rises at first, but then it drops as mexican pesos depreciate against u. s. dollars.
Answers: 1
Do you know the correct answer?
Your project to obtain charitable donations is now 36 days into a planned 46-day project. the projec...