Given the following information for a one-year project, answer the following questions. • planned value (pv) = $30,000 • earned value (ev) = $27,000 • actual cost (ac) = $25,000 • budget at completion (bac) = $150,000 1. what is the cost variance, schedule variance, cost performance index, and schedule performance index for the project? 2. is the project ahead of schedule or behind schedule? 3. is the project under budget or over budget? 4. use the cost performance index to calculate the estimate at completion (eac) for this project. is the project performing better or worse than planned? 5. use the schedule performance index to estimate how long it will take to finish this project.

answer
Answers: 3

Other questions on the subject: Business

image
Business, 22.06.2019 22:40, gracebuffum
In a fixed-term, level-payment reverse mortgage, sometimes called a reverse annuity mortgage, or ram, a lender agrees to pay the homeowner a monthly payment, or annuity, and expects to be repaid from the homeowner’s equity when he or she sells the home or obtains other financing to pay off the ram. consider a household that owns a $150,000 home free and clear of mortgage debt. the ram lender agrees to a $100,000 ram for 10 years at 6 percent. assume payments are made annually, at the beginning of each year to the homeowner. calculate the annual payment on the ram.
Answers: 1
image
Business, 23.06.2019 00:00, amanquen35
How do the percentages of the 65 customer satisfaction ratings in that actually fall into the intervals [formula62.mml ± s], [formula62.mml ± 2s], and [formula62.mml ± 3s] compare to those given by the empirical rule? do these comparisons indicate that the statistical inferences you made in parts b and c are reasonably valid? (round your answers to the nearest whole number. omit the "%" sign in your
Answers: 2
image
Business, 23.06.2019 02:30, mathiscool51
Organizations typically rely on schedules, such as hourly wages and annual reviews and raises.
Answers: 2
image
Business, 23.06.2019 15:00, mari048
Jenny​ walters, who owns a real estate​ agency, bought an old house to use as her business office. she found that the ceiling was poorly insulated and that the heat loss could be cut significantly if six inches of foam insulation were installed. she estimated that with the​ insulation, she could cut the heating bill by​ $80 per month and the​ air-conditioning cost by​ $70 per month. assuming that the summer season is three months​ (june, july, and​ august) of the year and that the winter season is another three months​ (december, january, and​ february) of the​ year, how much can jenny spend on insulation if she expects to keep the property for five​ years? assume that neither heating nor​ air-conditioning would be required during the fall and spring seasons. if she decides to install the​ insulation, it will be done at the beginning of may.​ jenny's interest rate is​ 6% compounded monthly.
Answers: 3
Do you know the correct answer?
Given the following information for a one-year project, answer the following questions. • planned va...

Questions in other subjects:

Konu
History, 05.07.2021 08:50