The expected completion time of a project is 40 weeks and the variance of its critical path activities is 9. what is the project completion time with a 75% certainty?

answer
Answers: 1

Other questions on the subject: Business

image
Business, 22.06.2019 06:00, Bloom247
According to herman, one of the differences of managing a nonprofit versus a for-profit corporation is
Answers: 1
image
Business, 22.06.2019 17:00, jaymoney0531
Can someone me ? i’ll mark the best answer brainliest : )
Answers: 1
image
Business, 22.06.2019 19:40, izzyisawesome5232
The following cost and inventory data are taken from the accounting records of mason company for the year just completed: costs incurred: direct labor cost $ 90,000 purchases of raw materials $ 134,000 manufacturing overhead $ 205,000 advertising expense $ 45,000 sales salaries $ 101,000 depreciation, office equipment $ 225,000 beginning of the year end of the year inventories: raw materials $ 8,100 $ 10,300 work in process $ 5,900 $ 21,000 finished goods $ 77,000 $ 25,800 required: 1. prepare a schedule of cost of goods manufactured. 2. prepare the cost of goods sold section of mason company’s income statement for the year.
Answers: 3
image
Business, 22.06.2019 23:30, bearbri4520
The upper-level managers of synergy technology are meeting for the week to look at the long-term company goals and overall direction of the organization. the ceo has expressed her concern over the economy and has told her managers to look closely at the environment outside the organization before making decisions and to be future oriented. in this meeting, top managers of synergy are
Answers: 2
Do you know the correct answer?
The expected completion time of a project is 40 weeks and the variance of its critical path activiti...

Questions in other subjects:

Konu
Mathematics, 04.09.2020 02:01
Konu
Mathematics, 04.09.2020 02:01
Konu
Mathematics, 04.09.2020 02:01