XYZ Ltd signs a contract on 30 June 2015, agreeing to build a bridge for ABC Limited at a
contract price of $40 million. XYZ Ltd estimates that construction costs will be as follows:
Year Ending Cost
30 June 2016 $10 000 000
30 June 2017 $16 000 000
30 June 2018 $ 6 000 000
$32 000 000
The contract provides that ABC will make payments on 30 June of each year as follows:
2016 $8 000 000
2017 $20 000 000
2018 $12 000 000
$40 000 000
XYZ now estimates at the beginning of the 2017 financial year that construction costs will be
as follows:
Year Ending Cost
30 June 2016 $10 000 000
30 June 2017 $21 000 000
30 June 2018 $15 000 000
$46 000 000
Required:
Calculate:
a) Percentage of completion for each of the three years. (4 marks)
b) Revenue to be recognised in each of the three years. (3 marks)
c) Gross profit/loss to be recognised in each of the three years. (3 marks)
Answers: 2
Arts, 22.06.2019 01:30, Wolfb21345
What does johnny give to ponyboy? a a comb b a letter c a copy of "gone with the wind." d some clothes
Answers: 2
Arts, 24.06.2019 09:30, Batzs3rdacct
In "a dream within a dream," which phrase is a context clue to the meaning of grasp / them with a tighter clasp?
Answers: 1
XYZ Ltd signs a contract on 30 June 2015, agreeing to build a bridge for ABC Limited at a
contract...
Social Studies, 28.12.2021 03:50
Mathematics, 28.12.2021 03:50
Biology, 28.12.2021 03:50
Computers and Technology, 28.12.2021 03:50
SAT, 28.12.2021 03:50