Why is the critical path critical?
a. any delay in the critical path delays the project finis...
Why is the critical path critical?
a. any delay in the critical path delays the project finish date.
b. it represents tasks in which resources are overallocated.
c. it represents tasks that are delayed.
d. the tasks on the critical path are the most important ones for achieving the project goal.